Choose a general contractor and architect by checking licenses, bonding capacity, insurance and similar completed projects first, then comparing contracts, not just prices. The standard AIA forms are B101 for the architect and A101 (stipulated sum) or A102 (cost plus fee with a guaranteed maximum price) for the contractor. Your construction lender will also review the contractor and, on larger projects, often holds back 10% of each draw until completion.
At a glance
- Owner-architect form
- AIA B101-2017
- Fixed price
- AIA A101-2017
- Cost plus fee with GMP
- AIA A102-2017, A133-2019
- Bonds
- AIA A312-2010, surety on Circular 570
- Draw paperwork
- AIA G702 and G703, lien waivers
Document names from AIA Contract Documents, checked Nov 13, 2026.
- The contract decides who pays for overruns. Under a stipulated sum (A101) or GMP (A102, A133) the contractor carries costs above the price; under cost plus fee without a GMP (A103) the owner does.
- Licenses are checked state by state. Each of 55 U.S. jurisdictions has an architecture board, per NCARB; contractor boards such as California's CSLB show license status and complaints online.
- Bonds need their own check. Ask for a surety letter on bonding capacity and confirm the surety on Treasury's Circular 570, last updated Aug 1, 2026.
- The lender controls the money. The FDIC's examiner manual describes monthly draws totaling 90% of value with 10% held back until completion on larger projects.
In this guide · 10 sections
- How do you choose a general contractor and architect for a development?
- Which construction contract type should a sponsor use?
- How do you check a contractor's license and bonding?
- How do you check an architect's license?
- How do construction draws work, and what will the lender require?
- What should you ask a contractor or architect before you hire them?
- What are the red flags when hiring a contractor or architect?
- What should be on a contractor and architect selection checklist?
- Which construction and design firms are listed in Relli's partner directory?
- What do sponsors ask about hiring contractors and architects?
The short version
How do you choose a general contractor and architect for a development?
Start with the checks that can end the conversation: a current license, bonding capacity, insurance and a record on projects of the same type and size. Then compare contracts, not just prices, because the contract decides who pays when costs run over. Bring your construction lender in early, since the lender will review the contractor and control every draw; the guide to choosing a commercial real estate lender covers when a debt broker helps on a construction loan.
- Pick a delivery method. Design-bid-build (architect first, then bid the drawings), design-build (one firm designs and builds) or a construction manager at risk working beside the architect.
- Hire the architect. Verify the license with the state architecture board and agree scope and fee in writing.
- Prequalify contractors. License, bonding capacity, insurance, financial strength, references and similar completed projects.
- Choose the contract type. Stipulated sum, cost plus fee with a guaranteed maximum price (GMP), or cost plus fee without one.
- Line up the lender's requirements. Draw schedule, inspections, lien waivers, retainage, bonds and builder's risk insurance.
Contracts
Which construction contract type should a sponsor use?
The American Institute of Architects (AIA) publishes standard forms for these agreements. The price structure is the key choice: it decides how much cost overrun risk the contractor carries and how much stays with your deal, which investors will test against the construction budget in your pro forma.
| Contract type | AIA document | How the price works | Who carries overruns |
|---|---|---|---|
| Stipulated sum (lump sum) | A101-2017 | One fixed price for the defined work | Contractor, except for owner changes |
| Cost plus fee with GMP | A102-2017 | Actual cost of the work plus a fee, capped at the GMP | Contractor above the GMP |
| Cost plus fee, no GMP | A103-2017 | Actual cost plus a fee, no cap | Owner |
| Construction manager as constructor | A133-2019 | Cost plus fee with a GMP, with the CM advising during design | Construction manager above the GMP |
| Owner and architect | B101-2017 | Design and construction-phase services for an agreed fee | Not a construction price |
AIA describes A103 as fitting projects where "the cost is not fully known at the commencement of construction," and A133 as the form where the construction manager "assumes financial responsibility for construction of the project." The A201-2017 General Conditions of the Contract for Construction sit under the A-series agreements and cover changes, payments, insurance and claims.
Worked example
A sponsor signs an A102 contract with a guaranteed maximum price of $20,000,000, which covers the cost of the work and the contractor's fee.
- Final cost plus fee comes in at $19,400,000: the owner pays $19,400,000. How any savings are shared is a term you negotiate.
- Final cost plus fee comes in at $20,600,000 with no owner-approved changes: the contractor absorbs the $600,000 above the GMP.
- The owner adds a clubhouse by change order: the GMP rises by the agreed change amount, and that cost is the owner's.
The GMP protects the budget only for the scope in the drawings. Unclear drawings turn into change orders.
Licenses and bonds
How do you check a contractor's license and bonding?
Contractor licensing is set by states, and sometimes cities, so start with the board where the project is. California's Contractors State License Board (CSLB), for example, runs an online lookup that shows a license's status and complaint disclosures. Search the company name and the license number on the contract, and confirm the license classification matches the work.
Bonds are a separate check. The SBA defines the three common construction bonds:
- Bid bond: "Ensures full payment and performance bonding from the contract bidder."
- Performance bond: "Ensures full completion of a contract by small business."
- Payment bond: "Ensures full payment to the suppliers and subcontractors."
Private projects do not always use bonds, but lenders on larger projects may require them. AIA's standard form is A312-2010 Performance Bond and Payment Bond. Ask the contractor for a letter from its surety stating its bonding capacity. Check that the surety appears on Treasury's Circular 570, the list of companies that write or reinsure federal bonds, last updated August 1, 2026. AIA's A305-2020 Contractor's Qualification Statement is a standard form for collecting the rest of a contractor's background.
Architects
How do you check an architect's license?
Architects are licensed by the jurisdiction where they practice. NCARB, the national council of architecture boards, says the 50 states, the District of Columbia, Puerto Rico, Guam, the Northern Mariana Islands and the U.S. Virgin Islands each have an architecture board, 55 in all. NCARB lists every board's contact details and links to license lookups.
Check the license of the architect who will seal the drawings, in the project's state, not just the firm's home state. Structural, civil and MEP engineers carry their own professional licenses, so check the engineer of record too. Ask the architect what construction-phase services are in the fee: site visits, submittal review and certifying the contractor's payment applications all matter once the lender starts funding draws.
The lender
How do construction draws work, and what will the lender require?
A construction loan is funded in stages, and the lender's controls shape your whole team. The FDIC's examination manual for bank examiners says that before a construction loan the bank should "investigate the character, expertise, and financial standing of all related parties," with files showing the developer, contractor and subcontractors can complete that type of project.
The same manual says the bank, builder and owner typically sign a building loan agreement. On larger projects, funds usually follow a progress payment plan of "monthly disbursements totaling 90 percent of the value with 10 percent held back until the project is completed." Supporting documents for commercial construction loans include title insurance, liability insurance, completion bonds and inspection or progress reports.
How the construction loan, the guarantees and the investors' equity fit together is covered in how to raise capital for real estate development.
In practice a monthly draw usually looks like this:
- The contractor submits a payment application, often on AIA G702 (Application and Certificate for Payment) with the G703 Continuation Sheet.
- The architect reviews and certifies the work claimed.
- The lender's inspector confirms progress on site.
- The contractor and major subcontractors deliver lien waivers for earlier payments.
- The title company updates title, and the lender funds the draw less retainage.
Lenders also want builder's risk insurance in place from the start of work. Fannie Mae's multifamily rules, for example, set it at 100% or more of completed value. The guide to investment property and syndication insurance covers builder's risk and the other policies.
Interviews
What should you ask a contractor or architect before you hire them?
- What projects of this type, size and location have you completed in the last five years, and can I call those owners?
- What is your bonding capacity, and who is your surety?
- Which license numbers will appear on the contract and permits?
- Which costs sit in the GMP, and what are the contingency and allowances?
- How do you price change orders, and what markup applies?
- Who is the project manager and superintendent, and are they committed for the whole job?
- For the architect: which construction-phase services are included, and how often will you visit the site?
- Have you worked with construction lenders and their inspectors on draws before?
Warning signs
What are the red flags when hiring a contractor or architect?
- A license that is expired, suspended, in another name or in the wrong classification.
- No surety letter, or a surety you cannot find on Circular 570.
- A bid far below the others with no clear scope explanation.
- Large deposits asked for before work or materials are delivered.
- Reluctance to provide lien waivers or follow the lender's draw process.
- An architect whose license is not in the project's state.
Checklist
What should be on a contractor and architect selection checklist?
- Delivery method chosen: design-bid-build, design-build or CM at risk.
- Architect and engineer licenses checked in the project's state.
- Contractor license checked with the state board, in the right classification.
- Surety letter on bonding capacity, surety checked on Circular 570.
- Qualification statement, financials and owner references reviewed.
- Contract type agreed (A101, A102, A103 or A133), with contingency and change order pricing.
- Builder's risk and liability insurance assigned in the contract.
- Draw process agreed with the lender: pay applications, inspections, lien waivers, retainage.
Directory
Which construction and design firms are listed in Relli's partner directory?
As of Nov 13, 2026, seven firms in the directory's Construction and Architecture categories list general contracting, design-build, architecture or building engineering for commercial or multi-unit projects, and one Consulting listing, a development consultant, fits here too. Each description and location comes from the firm's own Relli profile.
| Partner | What they do | Location | Link |
|---|---|---|---|
| Bingham Construction | Family-owned builder for commercial real estate in Southern California: tenant improvements, design-build, general contracting, preconstruction | San Diego, CA | Bingham Construction on Relli |
| Enhaus Design & Build | Design and construction under one team for Southern California homes and select commercial projects | Arcadia, CA | Enhaus Design & Build on Relli |
| Lowney Architecture | Architecture for residential and light commercial projects, including multi-unit housing and adaptive reuse | Oakland, CA | Lowney Architecture on Relli |
| Mazzetti | MEP engineering, energy modeling, sustainability and commissioning for owners and developers | Atlanta, GA | Mazzetti on Relli |
| Murow Development Consultants | Land development consulting: feasibility, cost estimating, entitlements, bid administration and construction management oversight | Irvine, CA | Murow Development Consultants on Relli |
| Nelson Structural Engineers | Structural analysis and design for commercial, institutional, residential and industrial buildings | Irvine, CA | Nelson Structural Engineers on Relli |
| Park West | Commercial general contractor for retail, interiors, industrial and education projects | Rancho Santa Margarita, CA | Park West on Relli |
Disclosure: Partners list for free. Relli approves each listing before it appears, but approval is not an endorsement; check licenses and references yourself.
Related services in the directory: Tangram Interiors (Santa Fe Springs, CA) lists interior architecture and space planning, and TRL Systems (Rancho Cucamonga, CA) lists fire life safety, security and IT systems for commercial buildings.
FAQ
What do sponsors ask about hiring contractors and architects?
What is a guaranteed maximum price contract?
A GMP contract pays the contractor its actual cost of the work plus a fee, up to a ceiling. If costs run above the GMP without owner-approved changes, the contractor absorbs the excess. AIA's standard form is A102-2017; A133-2019 is the version for a construction manager as constructor. Savings below the GMP are shared however the contract says.
Should a developer use a lump sum or cost-plus contract?
A stipulated sum (AIA A101) gives price certainty when the drawings are complete. Cost plus fee with a GMP (A102) suits projects that start before design is final but still need a ceiling. Cost plus fee without a GMP (A103) leaves overruns with the owner, so the budget has no ceiling.
How do I verify a contractor's license?
Search the contractor licensing board in the project's state, and the city if it licenses contractors too. California's CSLB lookup, for example, shows license status and complaint disclosures. Match the name and license number to the contract, confirm the classification fits the work, and check that the license stays active for the whole project.
What is retainage on a construction loan?
Retainage is part of each payment held back until the work is complete. The FDIC's examination manual describes a progress payment plan on larger projects of monthly disbursements totaling 90% of the value, with 10% held back until completion. The exact percentage and release terms are set in the loan and construction contracts.
Do I need a performance and payment bond on a private project?
Not always, but lenders on larger projects may require them. A performance bond backs completion of the contract, and a payment bond backs payment to subcontractors and suppliers. The AIA A312-2010 form covers both. Get a surety letter on the contractor's bonding capacity and check the surety on Treasury's Circular 570 list.
Sources
- List of all current AIA Contract Documents (A101-2017, A102-2017, A103-2017, A133-2019, A201-2017, A305-2020, A312-2010, B101-2017, G702-1992, G703-1992), AIA Contract Documents (accessed Nov 13, 2026)
- A-Series: Owner/Contractor Agreements, AIA Contract Documents (accessed Nov 13, 2026)
- State licensing boards, National Council of Architectural Registration Boards (NCARB) (accessed Nov 13, 2026)
- Check a license, California Contractors State License Board (accessed Nov 13, 2026)
- Surety bonds (bid, performance and payment bonds), U.S. Small Business Administration (accessed Nov 13, 2026)
- Surety bonds: Circular 570, Treasury's listing of approved sureties, U.S. Department of the Treasury, Bureau of the Fiscal Service (circular updated Aug 1, 2026 | accessed Nov 13, 2026)
- RMS Manual of Examination Policies, Section 3.2: Loans (construction loans), Federal Deposit Insurance Corporation (section dated May 2023 | accessed Nov 13, 2026)
- Multifamily Selling and Servicing Guide, Part II, Chapter 5, section 506.02: Builder's Risk Insurance, Fannie Mae (accessed Nov 13, 2026)
- Partner directory (Construction, Architecture and Consulting listing pages), Relli (accessed Nov 13, 2026)